Construction Project Schedule
The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.
SpreadsheetConstruction Project ManagementFree
A 15-working-day look-ahead with daily bars, milestones and inspections, constraint flags and a make-ready log for each activity.
Shown with sample data
A 15-working-day look-ahead with daily bars, milestones and inspections, constraint flags and a make-ready log for each activity.
The master schedule says what should happen; the look-ahead says what will happen in the next three weeks and what must be cleared first. List each activity with area, trade, start, finish and percent complete, and the daily timeline draws itself across 15 working days: done, planned, late, and a diamond for milestones and inspections. Constraints such as materials, inspections, RFIs or labour are flagged on each activity and tracked on a make-ready log with owners and need-by dates.
A short-interval schedule covering the next three weeks in daily detail, taken from the master schedule and refined with the trades. It is updated weekly and focuses on what is ready to be built.
Each day column shows Done for the share of the activity completed, Planned for the rest, Late for past days that are not finished, and a diamond for milestones and inspections. Days come from the start date on Settings.
Anything that must be in place before work can start: materials delivered, a prior activity finished, an RFI answered, a submittal approved, an inspection passed, labour or equipment available, or suitable weather.