Skip to content
GraviPointThe Centre of Productivity
  • AI AgentNew
  • Pricing
  • Community
Log inGet started free
TemplatesConstruction & EngineeringConstruction Project ManagementConstruction Project Schedule

SpreadsheetConstruction Project ManagementFree

Construction Project Schedule

The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.

Shown with sample data

Colour

Construction Project Schedule

The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.

Overall progress
31%
Weighted by duration
Behind schedule
4
Days to handover
114
Total slip so far
4
Days, on finished activities
Progress by phase
  • Pre-construction100%
  • Foundation100%
  • Structure70%
  • Envelope5.9%
Duration by activity (days)
  • Finishes and fixtures40
  • Framing and sheathing30
  • Insulation and drywall30
  • Electrical and plumbing rough-in26
  • Excavation and footings17
  • Roofing17
  • Slab pour and cure14
  • Windows and exterior doors12

How to use it

  1. 1List every activity in order with phase, crew, predecessor and planned dates.
  2. 2Update Complete each week and type the actual finish when an activity is done.
  3. 3Check anything flagged Behind and plan a recovery with the crew.
  4. 4Change the month headers and dates on the right to match your job.

In this workbook

  • About
  • What’s included
  • How to use
  • Questions
  • Related resources

About this template

A practical build programme. Each activity has a phase, crew or subcontractor, predecessor, planned start and finish, percent complete and actual finish. The schedule works out durations, compares progress with where you should be today, flags behind-schedule work, and shows any slip on finished activities. Month columns draw a simple bar chart across the job, coloured done, planned or late. Phase and progress summaries give the overall picture, with progress weighted by duration so long activities count for more.

Who it’s for

  • Residential and light commercial builds
  • Weekly site and client meetings
  • Spotting delays before they spread

What’s included

  • Schedule sheet: Every activity with dates, progress and status.
  • Phases sheet: Start, finish and progress for each phase.

How to use it

  1. 1List every activity in order with phase, crew, predecessor and planned dates.
  2. 2Update Complete each week and type the actual finish when an activity is done.
  3. 3Check anything flagged Behind and plan a recovery with the crew.
  4. 4Change the month headers and dates on the right to match your job.

Tips

  • Break activities longer than four weeks into smaller pieces so progress is easier to judge.
  • Inspections and long-lead materials often drive the programme: give them their own lines.

Questions

How is Behind decided?

An activity is behind if its finish date has passed without being complete, or its percent complete is more than 10 points below the share of its duration already used.

What is slip?

Actual finish minus planned finish, in days, for completed activities.

Related searchesconstruction schedulebuild programmegantt chartproject timelineconstruction planninglook-ahead

Details

Format
Spreadsheet
Category
Construction Project Management
Sheets
2
Setup
10 min
Level
Beginner
Price
Free

Download a copy

Downloads need a free account.

SpreadsheetConstruction Project ManagementFree

Construction Project Schedule

The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.

A free account keeps your copy safe so you can come back to it. Have one? Log in

Download a copy

Downloads need a free account.

Details

Format
Spreadsheet
Category
Construction Project Management
Sheets
2
Setup
10 min
Level
Beginner
Price
Free

Your copy is private to you.

More construction project management templates

View all
RFI Log2 sheets

Open RFIs

4

Overdue responses

2

Average days to answer

10.3

ABCD
1RFIRaisedSubjectCategory
2RFI-001Oct 5Slab edge detail at grid line C clashes with drainageStructural
3RFI-002Oct 9Door D14 hardware schedule missingArchitectural
4RFI-003Oct 20Ceiling void too shallow for specified ductwork, level 2Mechanical & electrical
5RFI-004Oct 28Confirm brick type for east elevation; sample rejectedArchitectural
RFIs
SpreadsheetConstruction Project Management

RFI Log

Track every request for information from question to answer, with due dates and cost and schedule impact.

10 min setupPreview
Schedule of Values & Payment Application2 sheets

Contract sum

$1,200,000

Completed to date

52%

Payment due this application

$173,070

ABCD
1ItemDescription of workCategoryScheduled value
21General conditions and supervisionGeneral conditions$85,000
32Site clearance and excavationSite work$62,000
43Foundations and slabStructure$148,000
54Structural steel frameStructure$215,000
Schedule of values
SpreadsheetConstruction Project Management

Schedule of Values & Payment Application

Bill progress against each line of the contract: work completed, stored materials, retainage and payment due.

10 min setupPreview
Three-Week Look-Ahead Schedule
Task
Mon W1Tue W1Wed W1Thu W1Fri W1Mon W2Tue W2Wed W2Thu W2Fri W2
Frame level 2 exterior walls
Frame level 2 interior partitions
Set roof trusses
Roof sheathing and underlayment
Electrical rough-in
Plumbing top-out
SpreadsheetConstruction Project Management

Three-Week Look-Ahead Schedule

A 15-working-day look-ahead with daily bars, milestones and inspections, constraint flags and a make-ready log for each activity.

25 min setupPreview

Practical guides and new resources, monthly.

One short email with new templates, calculators and how-tos. Unsubscribe any time.

GraviPointThe Centre of Productivity

Find the right resource. Make it work for you. Get things done with spreadsheets, documents, forms and calculators you can use right in your browser.

support@gravipoint.com
  • @gravipoint
  • @GraviPoint
  • GraviPoint
  • 𝕏@gravipoint

Templates

  • All templates
  • Budgets & expenses
  • Invoices & billing
  • Project management
  • HR & people
  • Inventory & stock
  • Sales & CRM
  • Financial calculators

Popular

  • Monthly budget
  • Invoice
  • Employee shift schedule
  • Weekly timesheet
  • Project plan & Gantt chart
  • Inventory tracker
  • Expense report
  • Mortgage calculator

Solutions

  • Individuals & households
  • Freelancers & consultants
  • Founders & startups
  • Small business owners
  • Teams & operations
  • Students & educators

Company

  • About
  • Features
  • Pricing
  • Community
  • Journal
  • Contact
© 2026 GraviPoint. All rights reserved.
  • Privacy
  • Terms
  • Help centre
  • FAQ