Skip to content
GraviPointThe Centre of Productivity
  • AI AgentNew
  • Pricing
  • Community
Log inGet started free
TemplatesConstruction & EngineeringConstruction Project ManagementSchedule of Values & Payment Application

SpreadsheetConstruction Project ManagementFree

Schedule of Values & Payment Application

Bill progress against each line of the contract: work completed, stored materials, retainage and payment due.

Shown with sample data

Colour

Schedule of Values & Payment Application

Bill progress against each line of the contract: work completed, stored materials, retainage and payment due.

Contract sum
$1,200,000
Completed to date
52%
Payment due this application
$173,070
This period less 10% retainage
Retainage held
$62,840
Percent complete by item
  • Site clearance and excavation100%
  • Foundations and slab100%
  • Structural steel frame90%
  • General conditions and supervision50%
  • Roofing49.2%
  • Exterior walls and glazing42%
  • Mechanical, electrical and plumbing rough-in25%

How to use it

  1. 1Agree the schedule of values with the owner before the first application.
  2. 2Move last month’s “this period” into “previous applications”.
  3. 3Enter this period’s work and stored materials.
  4. 4Attach photos, delivery notes and lien waivers as required.

In this workbook

  • About
  • What’s included
  • How to use
  • Questions
  • Related resources

About this template

The standard way to get paid on a construction contract. Break the contract sum into line items, then each month enter work completed and materials stored; the sheet calculates percent complete, balance to finish, retainage and the payment due for this application.

Who it’s for

  • Monthly progress billing
  • Lender draw requests
  • Checking a subcontractor’s application against progress on site

What’s included

  • Schedule of values sheet: One row per line of the contract sum.
  • Summary by Category sheet: Scheduled value and Completed and stored and the number of entries for each category, calculated from the Schedule of values sheet.

How to use it

  1. 1Agree the schedule of values with the owner before the first application.
  2. 2Move last month’s “this period” into “previous applications”.
  3. 3Enter this period’s work and stored materials.
  4. 4Attach photos, delivery notes and lien waivers as required.

Questions

What is retainage?

A percentage of each payment, often 5–10%, held back until the work is substantially complete. This sheet uses 10%; change the formula if your contract differs.

Related searchesschedule of valuespayment applicationprogress billingconstruction draw requestpay app template

Details

Format
Spreadsheet
Category
Construction Project Management
Sheets
2
Setup
10 min
Level
Advanced
Price
Free

Download a copy

Downloads need a free account.

SpreadsheetConstruction Project ManagementFree

Schedule of Values & Payment Application

Bill progress against each line of the contract: work completed, stored materials, retainage and payment due.

A free account keeps your copy safe so you can come back to it. Have one? Log in

Download a copy

Downloads need a free account.

Details

Format
Spreadsheet
Category
Construction Project Management
Sheets
2
Setup
10 min
Level
Advanced
Price
Free

Your copy is private to you.

More construction project management templates

View all
Construction Project Schedule
Task
SepOctNovDecJanFebMar
Permits and mobilisation
Excavation and footings
Slab pour and cure
Framing and sheathing
Roofing
Windows and exterior doors
SpreadsheetConstruction Project Management

Construction Project Schedule

The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.

10 min setupPreview
RFI Log2 sheets

Open RFIs

4

Overdue responses

2

Average days to answer

10.3

ABCD
1RFIRaisedSubjectCategory
2RFI-001Oct 5Slab edge detail at grid line C clashes with drainageStructural
3RFI-002Oct 9Door D14 hardware schedule missingArchitectural
4RFI-003Oct 20Ceiling void too shallow for specified ductwork, level 2Mechanical & electrical
5RFI-004Oct 28Confirm brick type for east elevation; sample rejectedArchitectural
RFIs
SpreadsheetConstruction Project Management

RFI Log

Track every request for information from question to answer, with due dates and cost and schedule impact.

10 min setupPreview
Three-Week Look-Ahead Schedule
Task
Mon W1Tue W1Wed W1Thu W1Fri W1Mon W2Tue W2Wed W2Thu W2Fri W2
Frame level 2 exterior walls
Frame level 2 interior partitions
Set roof trusses
Roof sheathing and underlayment
Electrical rough-in
Plumbing top-out
SpreadsheetConstruction Project Management

Three-Week Look-Ahead Schedule

A 15-working-day look-ahead with daily bars, milestones and inspections, constraint flags and a make-ready log for each activity.

25 min setupPreview

Practical guides and new resources, monthly.

One short email with new templates, calculators and how-tos. Unsubscribe any time.

GraviPointThe Centre of Productivity

Find the right resource. Make it work for you. Get things done with spreadsheets, documents, forms and calculators you can use right in your browser.

support@gravipoint.com
  • @gravipoint
  • @GraviPoint
  • GraviPoint
  • 𝕏@gravipoint

Templates

  • All templates
  • Budgets & expenses
  • Invoices & billing
  • Project management
  • HR & people
  • Inventory & stock
  • Sales & CRM
  • Financial calculators

Popular

  • Monthly budget
  • Invoice
  • Employee shift schedule
  • Weekly timesheet
  • Project plan & Gantt chart
  • Inventory tracker
  • Expense report
  • Mortgage calculator

Solutions

  • Individuals & households
  • Freelancers & consultants
  • Founders & startups
  • Small business owners
  • Teams & operations
  • Students & educators

Company

  • About
  • Features
  • Pricing
  • Community
  • Journal
  • Contact
© 2026 GraviPoint. All rights reserved.
  • Privacy
  • Terms
  • Help centre
  • FAQ