Subcontract Agreement
This Subcontract Agreement (the "Subcontract") is made on [date] between:
Contractor: [General Contractor legal name], a [state] [corporation / LLC], licence no. [number], of [address] ("Contractor"); and
Subcontractor: [Subcontractor legal name], a [state] [corporation / LLC], licence no. [number], of [address] ("Subcontractor").
Project | [Project name] at [project address] |
Owner | [Owner legal name] |
Prime contract | Agreement between Owner and Contractor dated [date] (the "Prime Contract") |
Architect / engineer | [Name] |
Subcontract work | [Trade, e.g. electrical systems] as described in Exhibit A |
Subcontract price | [$ amount] |
Recitals
A. Contractor has entered into the Prime Contract with Owner to construct the Project. B. Subcontractor is licensed and experienced in the work described in Exhibit A and wishes to perform it on the terms below.
1. Definitions
1.1 "Work" means all labour, materials, equipment, supervision and services required to complete the scope in Exhibit A, and anything reasonably inferable from the Subcontract Documents as necessary to produce the intended result. 1.2 "Subcontract Documents" means this Subcontract, its exhibits, the Prime Contract, and the drawings, specifications, addenda and modifications listed in Exhibit A. 1.3 "Change Order" means a written order signed by Contractor changing the Work, the Subcontract Price or the time for performance.
2. Subcontract documents and flow-down
2.1 Subcontractor has reviewed the Subcontract Documents and is bound to Contractor by them, and assumes toward Contractor all obligations Contractor assumes toward Owner under the Prime Contract, so far as they apply to the Work. 2.2 If the Subcontract Documents conflict, the stricter requirement or higher quality applies unless Contractor directs otherwise in writing. 2.3 Subcontractor shall report any error, inconsistency or omission it discovers in the documents to Contractor promptly and before proceeding with affected Work.
3. Scope of work
3.1 Subcontractor shall perform the Work described in Exhibit A in a good and workmanlike manner, in accordance with the Subcontract Documents and all applicable codes. 3.2 Subcontractor shall furnish all permits and inspections customarily obtained by its trade unless Exhibit A states otherwise.
4. Subcontract price
4.1 Contractor shall pay Subcontractor [$ amount] (the "Subcontract Price"), subject to additions and deductions by Change Order. 4.2 The Subcontract Price includes all taxes, fees, permits (as stated in Exhibit A), freight, and overhead and profit.
5. Payment
5.1 Payment applications. By the [25th] day of each month, Subcontractor shall submit an application for payment for Work completed and materials suitably stored, based on the schedule of values in Exhibit B, together with a conditional lien waiver for the amount requested and unconditional lien waivers for all previous payments. 5.2 Retainage. Contractor shall retain [10]% of each progress payment. [When the Work is 50% complete and progressing satisfactorily, retainage on further payments shall be reduced to 5%.] Retainage shall be paid with final payment, [or as required by applicable law]. 5.3 Timing. Contractor shall pay approved amounts within [7] days after Contractor receives payment from Owner for that Work [, and in any event within the time required by applicable prompt payment law]. Choose pay-when-paid or pay-if-paid wording only after checking enforceability in [state]. 5.4 Final payment. Final payment is due when the Work is complete and accepted, and Subcontractor has delivered final unconditional lien waivers from itself and its lower-tier subcontractors and suppliers, as-built drawings, warranties, operation and maintenance manuals, and any other closeout documents required. 5.5 Withholding. Contractor may withhold payment to the extent reasonably necessary to protect it from defective Work not remedied, third-party claims or liens, failure to pay lower tiers, or reasonable evidence the Work cannot be completed for the unpaid balance.
6. Schedule
6.1 Time is of the essence. Subcontractor shall start the Work on [date or within X days of notice], keep pace with the Project schedule and complete the Work by [date]. 6.2 Subcontractor shall provide manpower and equipment sufficient to meet the Contractor’s schedule and three-week look-ahead, and attend coordination meetings. 6.3 If Subcontractor is delayed by causes beyond its control, it shall give written notice within [5] days of the start of the delay to be considered for an extension of time. Liquidated damages assessed by Owner and caused by Subcontractor shall be borne by Subcontractor.
7. Changes
7.1 Contractor may order changes in the Work. No change shall be paid unless authorised in advance by a written Change Order or written directive signed by Contractor. 7.2 Subcontractor shall submit a priced proposal within [7] days of a request, broken down by labour, materials, equipment and lower-tier costs, with overhead and profit not exceeding [10]% combined. 7.3 Claims for additional cost or time must be submitted in writing within [7] days of the event, or within the time needed for Contractor to give notice under the Prime Contract, whichever is shorter.
8. Insurance
8.1 Before starting Work, Subcontractor shall provide certificates and endorsements showing the insurance in Exhibit C, maintained until final completion and, for completed operations, for [3] years after. 8.2 Contractor, Owner and others required by the Prime Contract shall be additional insureds on a primary and non-contributory basis, with a waiver of subrogation in their favour.
9. Indemnity
To the fullest extent permitted by law, Subcontractor shall defend, indemnify and hold harmless Contractor, Owner and their agents and employees from claims, damages, losses and expenses, including reasonable attorneys’ fees, arising out of or resulting from performance of the Work, to the extent caused by the negligent acts or omissions of Subcontractor, its lower tiers or anyone for whose acts they are liable.
10. Safety
10.1 Subcontractor is responsible for the safety of its employees and lower tiers and shall comply with OSHA and all applicable safety laws and Contractor’s site safety program. 10.2 Subcontractor shall provide a site-specific safety plan before mobilising, name a competent person on site, attend site inductions and toolbox talks, and report all injuries and near misses to Contractor the same day. 10.3 Contractor may stop any unsafe work without liability for resulting delay or cost.
11. Quality and warranty
11.1 Subcontractor warrants that materials will be new and of good quality and that the Work will be free from defects and conform to the Subcontract Documents. 11.2 Subcontractor shall correct defective Work promptly on notice for [one (1)] year after substantial completion of the Project, or longer if required by the Prime Contract or a manufacturer’s warranty, at no cost to Contractor.
12. Liens and payment of lower tiers
12.1 Subcontractor shall pay its workers, lower-tier subcontractors and suppliers promptly and keep the Project free of liens arising from the Work. 12.2 If a lien is filed by anyone claiming through Subcontractor, Subcontractor shall have it released or bonded off within [10] days of notice, failing which Contractor may do so and deduct the cost.
13. Default and termination
13.1 For cause. If Subcontractor fails to perform any obligation and does not begin to cure within [48 hours] and complete the cure within [7] days of written notice, Contractor may terminate this Subcontract or supplement Subcontractor’s forces, and recover the reasonable additional cost of completion. 13.2 For convenience. Contractor may terminate for convenience on [7] days’ written notice, paying for Work properly performed, materials delivered and reasonable demobilisation costs, but not anticipated profit on unperformed Work. 13.3 Suspension. Contractor may suspend the Work in writing; reasonable costs of a suspension not caused by Subcontractor will be adjusted by Change Order.
14. Dispute resolution
14.1 The parties shall first try to resolve disputes by good-faith negotiation between senior representatives within [14] days. 14.2 Unresolved disputes shall go to mediation, then to [binding arbitration under the construction rules of the American Arbitration Association / litigation in the courts of [county, state]]. Where a dispute involves Owner, Subcontractor agrees to be bound by the procedure and outcome under the Prime Contract so far as it relates to the Work. 14.3 Subcontractor shall continue the Work during any dispute, and Contractor shall continue to pay undisputed amounts.
15. Compliance and independent contractor status
15.1 Subcontractor shall hold all licences required for the Work and comply with all laws, including wage, tax, immigration, environmental and equal-opportunity laws. 15.2 Subcontractor is an independent contractor and is solely responsible for its employees’ wages, benefits, taxes and workers’ compensation.
16. General
16.1 Assignment. Subcontractor shall not assign this Subcontract or sublet the whole of the Work without Contractor’s written consent. 16.2 Notices. Notices shall be in writing and delivered by hand, courier or email with confirmation to the addresses above. 16.3 Governing law. This Subcontract is governed by the laws of [State], where the Project is located. 16.4 Entire agreement. This Subcontract, with its exhibits, is the entire agreement between the parties on its subject and supersedes all prior proposals and understandings. It may be amended only in writing signed by both parties. 16.5 Severability. If any provision is held unenforceable, the rest remain in force and the provision shall be enforced to the maximum extent permitted.
Signatures
Contractor | Subcontractor |
|---|---|
[Company name] | [Company name] |
By: ______________________ | By: ______________________ |
Name and title: [ ] | Name and title: [ ] |
Date: [ ] | Date: [ ] |
Exhibit A: Scope of work
Included: [e.g. complete electrical systems per drawings E-001 to E-402 dated [date], including service, distribution, branch circuits, lighting and controls, fire alarm rough-in, temporary power].
Excluded: [e.g. utility company charges, low-voltage data cabling, owner-furnished light fixtures (install only included)].
Furnished by others: [items supplied by Contractor or Owner].
Permits and inspections: [trade permit by Subcontractor].
Exhibit B: Schedule of values
Item | Description | Value |
|---|---|---|
1 | Mobilisation and submittals | [$ ] |
2 | Underground and service | [$ ] |
3 | Rough-in | [$ ] |
4 | Trim and devices | [$ ] |
5 | Testing, closeout and as-builts | [$ ] |
Total Subcontract Price | [$ ] |
Exhibit C: Insurance requirements
Coverage | Minimum limits |
|---|---|
Commercial general liability | [$1,000,000] per occurrence / [$2,000,000] aggregate, including completed operations |
Business automobile liability | [$1,000,000] combined single limit |
Workers’ compensation | Statutory limits for [state] |
Employer’s liability | [$1,000,000] each accident |
Umbrella / excess liability | [$5,000,000] |
This template is for general information and is not legal advice. Laws vary by [state/country]; have a qualified lawyer review it before signing.