Construction Project Schedule
The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.
SpreadsheetConstruction Project ManagementFree
Daily crew hours by worker and cost code with regular and overtime pay, labour burden, and hours against budget for every code.
Shown with sample data
Daily crew hours by worker and cost code with regular and overtime pay, labour burden, and hours against budget for every code.
Labour is the cost that moves most on a job, and you can only control it if hours are booked to the right cost code every day. Foremen enter each worker’s regular and overtime hours against a cost code; rates come from the crew list, overtime and labour burden are applied from Settings, and the cost code sheet compares hours and cost to date with budget, uses percent complete to forecast hours at completion, and flags codes heading over.
A code from the job budget (often based on CSI MasterFormat divisions, such as 03 30 00 cast-in-place concrete) used to track cost by activity, so you can compare actual cost with the estimate.
Employer costs on top of wages: payroll taxes, workers’ compensation, general liability on payroll, health insurance and other benefits. For construction it is often 25–45% of wages.
Hours to date ÷ percent complete. If 300 hours have produced 40% of the work, about 750 hours will be needed to finish.