TemplatesConstruction & EngineeringConstruction Project ManagementConstruction Meeting Minutes

DocumentConstruction Project ManagementFree

Construction Meeting Minutes

OAC meeting minutes with attendance, safety, schedule, numbered old and new business items, action owners, due dates and a corrections clause.

Shown with sample data

Colour

OAC Meeting Minutes: Meeting No. [12]

Project

[Riverside Medical Office Building]

Project number

[GC-2604]

Date and time

[Tuesday 17 Nov 2026, 10:00–11:15]

Location

[Site office trailer / video call]

Minutes prepared by

[Name, Project Manager, General Contractor]

Attendance

Name

Company

Role

Present

[Name]

[Owner LLC]

Owner’s representative

✓

[Name]

[Architect firm]

Project architect

✓

[Name]

[General Contractor]

Project manager

✓

[Name]

[General Contractor]

Superintendent

✓

[Name]

[Electrical sub]

Project manager

✓

[Name]

[Mechanical sub]

Project manager

Absent

Distribution: all attendees, [structural engineer], [MEP engineer], [lender’s inspector].

1. Safety

  • No recordable incidents since meeting 11. Total project hours: [18,420]; days without a lost-time injury: [142].

  • Near miss on [12 Nov]: unsecured plywood sheet lifted by wind at level 2. Toolbox talk on material securing given [13 Nov].

2. Approval of previous minutes

Minutes of meeting 11 approved without corrections.

3. Schedule

  • Overall progress [46%] against [49%] planned. Level 2 framing [3 working days] behind due to wind days on [5–6 Nov].

  • Recovery: framing crew adding Saturday shifts [21 and 28 Nov]. Dry-in still forecast for [11 Dec].

  • Three-week look-ahead issued with these minutes. Critical items: roof trusses delivery [23 Nov], level 1 MEP rough-in inspection [2 Dec].

4. Old business

Item

Description

Responsible

Due

Status

9.03

Owner to confirm exterior cladding colour (sample panels on site)

Owner

[10 Nov]

Closed: Colour "Slate Grey" confirmed [12 Nov]

10.02

Architect to answer RFI 027 (beam pocket at grid C/4)

Architect

[13 Nov]

Closed: answered [11 Nov], no cost impact

10.05

Electrical sub to submit revised lighting fixture submittal

Electrical sub

[14 Nov]

Open: received [16 Nov], under review

11.01

GC to price relocation of exam room sinks (Owner request)

GC

[17 Nov]

Open: proposal issued today, PCO 014 [$6,840], 2 days

11.04

Owner to confirm IT vendor and data closet requirements

Owner

[20 Nov]

Open

5. New business

Item

Description

Responsible

Due

Status

12.01

Utility company has moved transformer energisation to [15 Jan]. GC to assess temporary power cost and impact on commissioning

GC

[24 Nov]

Open

12.02

Architect to issue ASI for revised reception desk layout

Architect

[24 Nov]

Open

12.03

Mechanical sub absent; GC to confirm rooftop unit delivery date in writing

GC

[19 Nov]

Open

12.04

Owner requests weekly photo report; GC to start from [24 Nov]

GC

[24 Nov]

Open

6. RFIs and submittals

Type

Open

Overdue

Notes

RFIs

[4]

[1]

RFI 031 (fire damper access) overdue from MEP engineer

Submittals

[7]

[0]

Lighting fixtures and roofing membrane under review

7. Change orders

No.

Description

Amount

Days

Status

CO 006

Added exterior lighting at parking lot

[$12,450]

0

Executed

PCO 013

Unforeseen rock at elevator pit

[$18,900]

4

Pending Owner approval

PCO 014

Relocate exam room sinks

[$6,840]

2

Issued today

8. Inspections and quality

  • Level 1 framing inspection passed [10 Nov].

  • Concrete cylinder breaks for level 2 slab: 7-day results [3,420 psi], on track for 4,000 psi at 28 days.

9. Owner and architect items

  • Owner reminded that furniture vendor will need site access from [1 Mar 2027].

10. Next meeting

[Tuesday 1 Dec 2026, 10:00, site office trailer.]

These minutes are the preparer’s understanding of the discussion and decisions. They will be taken as accurate unless written corrections are received by [the preparer] within [5] business days of issue.

Text in [brackets] is yours to replace.

  • About
  • What’s included
  • How to use
  • Questions
  • Related resources

About this template

Construction meeting minutes become part of the project record and are often read later in disputes, so they need numbered items that carry forward until closed, a responsible party and due date for every action, and a clause that makes them accurate unless corrected. This OAC (owner-architect-contractor) template includes attendance and distribution, safety, schedule and look-ahead, old business carried from previous meetings, new business, RFIs, submittals, change orders, inspections and the next meeting.

Who it’s for

  • Weekly or biweekly OAC meetings
  • Subcontractor coordination meetings
  • Pre-construction and kick-off meetings
  • Keeping a defensible project record

What’s included

  • Attendance
  • 1. Safety
  • 2. Approval of previous minutes
  • 3. Schedule
  • 4. Old business
  • 5. New business
  • 6. RFIs and submittals
  • 7. Change orders
  • 8. Inspections and quality
  • 9. Owner and architect items

How to use it

  1. 1Number every item meeting.item (for example 12.04 is item 4 first raised at meeting 12) and keep the number until it closes.
  2. 2Copy all open items from the last minutes into Old business and update their status.
  3. 3Record decisions and actions, not conversations: who will do what by when.
  4. 4Issue the minutes within 48 hours to everyone on the distribution list.
  5. 5Ask for written corrections within the stated period and note any corrections at the next meeting.

Tips

  • Write "Owner to confirm tile selection by 24 Nov" rather than "tile discussed". Vague minutes protect nobody.
  • Do not record anything as agreed that changes cost or time unless it is followed by a change order; note "CO to follow".
  • Keep closed items in the minutes once, marked Closed, then drop them from the next issue.

Questions

Who writes construction meeting minutes?

Usually the general contractor’s project manager or the architect, depending on the contract. AIA A201 does not assign the task, so confirm it at the kick-off meeting.

Are meeting minutes legally binding?

They are not a contract, but undisputed minutes are strong evidence of what was decided and when. That is why the corrections clause matters.

What is an OAC meeting?

A regular meeting of the owner, architect and contractor (and key subcontractors as needed) to review progress, schedule, open issues, RFIs, submittals and changes.

Related searchesconstruction meeting minutes templateoac meeting minutesowner architect contractor meetingsite meeting minutesprogress meeting minutes constructionconstruction meeting agenda

Details

Format
Document
Category
Construction Project Management
Setup
30 min
Level
Intermediate
Price
Free

Download a copy

Downloads need a free account.

DocumentConstruction Project ManagementFree

Construction Meeting Minutes

OAC meeting minutes with attendance, safety, schedule, numbered old and new business items, action owners, due dates and a corrections clause.

A free account keeps your copy safe so you can come back to it. Have one? Log in

Download a copy

Downloads need a free account.

Details

Format
Document
Category
Construction Project Management
Setup
30 min
Level
Intermediate
Price
Free

Your copy is private to you.

More construction project management templates

View all
Construction Project Schedule
Task
SepOctNovDecJanFebMar
Permits and mobilisation
Excavation and footings
Slab pour and cure
Framing and sheathing
Roofing
Windows and exterior doors
SpreadsheetConstruction Project Management

Construction Project Schedule

The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.

10 min setupPreview
RFI Log2 sheets

Open RFIs

4

Overdue responses

2

Average days to answer

10.3

ABCD
1RFIRaisedSubjectCategory
2RFI-001Oct 5Slab edge detail at grid line C clashes with drainageStructural
3RFI-002Oct 9Door D14 hardware schedule missingArchitectural
4RFI-003Oct 20Ceiling void too shallow for specified ductwork, level 2Mechanical & electrical
5RFI-004Oct 28Confirm brick type for east elevation; sample rejectedArchitectural
RFIs
SpreadsheetConstruction Project Management

RFI Log

Track every request for information from question to answer, with due dates and cost and schedule impact.

10 min setupPreview
Schedule of Values & Payment Application2 sheets

Contract sum

$1,200,000

Completed to date

52%

Payment due this application

$173,070

ABCD
1ItemDescription of workCategoryScheduled value
21General conditions and supervisionGeneral conditions$85,000
32Site clearance and excavationSite work$62,000
43Foundations and slabStructure$148,000
54Structural steel frameStructure$215,000
Schedule of values
SpreadsheetConstruction Project Management

Schedule of Values & Payment Application

Bill progress against each line of the contract: work completed, stored materials, retainage and payment due.

10 min setupPreview

Practical guides and new resources, monthly.

One short email with new templates, calculators and how-tos. Unsubscribe any time.

GraviPointThe Centre of Productivity

Find the right resource. Make it work for you. Get things done with spreadsheets, documents, forms and calculators you can use right in your browser.

support@gravipoint.com
  • @gravipoint
  • @GraviPoint
  • GraviPoint
  • 𝕏@gravipoint

Templates

  • All templates
  • Budgets & expenses
  • Invoices & billing
  • Project management
  • HR & people
  • Inventory & stock
  • Sales & CRM
  • Financial calculators

Popular

  • Monthly budget
  • Invoice
  • Employee shift schedule
  • Weekly timesheet
  • Project plan & Gantt chart
  • Inventory tracker
  • Expense report
  • Mortgage calculator

Solutions

  • Individuals & households
  • Freelancers & consultants
  • Founders & startups
  • Small business owners
  • Teams & operations
  • Students & educators

Company

  • About
  • Features
  • Pricing
  • Community
  • Journal
  • Contact
© 2026 GraviPoint. All rights reserved.
  • Privacy
  • Terms
  • Help centre
  • FAQ