OAC Meeting Minutes: Meeting No. [12]
Project | [Riverside Medical Office Building] |
Project number | [GC-2604] |
Date and time | [Tuesday 17 Nov 2026, 10:00–11:15] |
Location | [Site office trailer / video call] |
Minutes prepared by | [Name, Project Manager, General Contractor] |
Attendance
Name | Company | Role | Present |
|---|---|---|---|
[Name] | [Owner LLC] | Owner’s representative | ✓ |
[Name] | [Architect firm] | Project architect | ✓ |
[Name] | [General Contractor] | Project manager | ✓ |
[Name] | [General Contractor] | Superintendent | ✓ |
[Name] | [Electrical sub] | Project manager | ✓ |
[Name] | [Mechanical sub] | Project manager | Absent |
Distribution: all attendees, [structural engineer], [MEP engineer], [lender’s inspector].
1. Safety
No recordable incidents since meeting 11. Total project hours: [18,420]; days without a lost-time injury: [142].
Near miss on [12 Nov]: unsecured plywood sheet lifted by wind at level 2. Toolbox talk on material securing given [13 Nov].
2. Approval of previous minutes
Minutes of meeting 11 approved without corrections.
3. Schedule
Overall progress [46%] against [49%] planned. Level 2 framing [3 working days] behind due to wind days on [5–6 Nov].
Recovery: framing crew adding Saturday shifts [21 and 28 Nov]. Dry-in still forecast for [11 Dec].
Three-week look-ahead issued with these minutes. Critical items: roof trusses delivery [23 Nov], level 1 MEP rough-in inspection [2 Dec].
4. Old business
Item | Description | Responsible | Due | Status |
|---|---|---|---|---|
9.03 | Owner to confirm exterior cladding colour (sample panels on site) | Owner | [10 Nov] | Closed: Colour "Slate Grey" confirmed [12 Nov] |
10.02 | Architect to answer RFI 027 (beam pocket at grid C/4) | Architect | [13 Nov] | Closed: answered [11 Nov], no cost impact |
10.05 | Electrical sub to submit revised lighting fixture submittal | Electrical sub | [14 Nov] | Open: received [16 Nov], under review |
11.01 | GC to price relocation of exam room sinks (Owner request) | GC | [17 Nov] | Open: proposal issued today, PCO 014 [$6,840], 2 days |
11.04 | Owner to confirm IT vendor and data closet requirements | Owner | [20 Nov] | Open |
5. New business
Item | Description | Responsible | Due | Status |
|---|---|---|---|---|
12.01 | Utility company has moved transformer energisation to [15 Jan]. GC to assess temporary power cost and impact on commissioning | GC | [24 Nov] | Open |
12.02 | Architect to issue ASI for revised reception desk layout | Architect | [24 Nov] | Open |
12.03 | Mechanical sub absent; GC to confirm rooftop unit delivery date in writing | GC | [19 Nov] | Open |
12.04 | Owner requests weekly photo report; GC to start from [24 Nov] | GC | [24 Nov] | Open |
6. RFIs and submittals
Type | Open | Overdue | Notes |
|---|---|---|---|
RFIs | [4] | [1] | RFI 031 (fire damper access) overdue from MEP engineer |
Submittals | [7] | [0] | Lighting fixtures and roofing membrane under review |
7. Change orders
No. | Description | Amount | Days | Status |
|---|---|---|---|---|
CO 006 | Added exterior lighting at parking lot | [$12,450] | 0 | Executed |
PCO 013 | Unforeseen rock at elevator pit | [$18,900] | 4 | Pending Owner approval |
PCO 014 | Relocate exam room sinks | [$6,840] | 2 | Issued today |
8. Inspections and quality
Level 1 framing inspection passed [10 Nov].
Concrete cylinder breaks for level 2 slab: 7-day results [3,420 psi], on track for 4,000 psi at 28 days.
9. Owner and architect items
Owner reminded that furniture vendor will need site access from [1 Mar 2027].
10. Next meeting
[Tuesday 1 Dec 2026, 10:00, site office trailer.]
These minutes are the preparer’s understanding of the discussion and decisions. They will be taken as accurate unless written corrections are received by [the preparer] within [5] business days of issue.