TemplatesConstruction & EngineeringConstruction Project ManagementChange Order Form

DocumentConstruction Project ManagementFree

Change Order Form

Document a change to the construction contract with description, reason, cost breakdown with markup, contract sum reconciliation, time impact and approvals.

Shown with sample data

Colour

Change Order No. [007]

Project

[Riverside Medical Office Building]

Project address

[1200 River Road, City, State ZIP]

Contract date

[12 Mar 2026]

Contract for

[General construction]

Owner

[Riverside Health Properties LLC]

Contractor

[Keystone Builders Inc.]

Architect

[Hale Design Studio]

Date of this change order

[17 Nov 2026]

1. Description of change

Describe exactly what is added, deleted or changed, with locations and quantities. Relocate sinks and casework in exam rooms 104, 106 and 108 from the north to the east wall as shown on ASI-009, including relocated waste, vent and water lines in the slab, new wall blocking, patching the slab and moving two electrical receptacles per room.

2. Reason for change

☐ Owner request ☐ Unforeseen site condition ☐ Design error or omission ☐ Code or authority requirement ☐ Value engineering ☐ Other: [ ]

[Owner request to improve clinician workflow following mock-up review on 4 Nov 2026.]

3. References

Document

Number

Date

Architect’s supplemental instruction

[ASI-009]

[6 Nov 2026]

Contractor’s proposal

[PCO 014]

[17 Nov 2026]

Drawings affected

[A-201, P-101, E-101]

[Rev 3]

Related RFI

[None]

4. Cost breakdown

Item

Quantity and basis

Amount

Labour

[38 h × $72/h (carpentry, demolition, patching)]

[$2,736]

Materials

[Blocking, slab patch, fittings]

[$640]

Equipment

[Concrete saw and core drill, 1 day]

[$310]

Subcontract: plumbing

[Relocate waste, vent and water, 3 rooms]

[$2,180]

Subcontract: electrical

[Relocate 6 receptacles]

[$420]

Subtotal

[$6,286]

Overhead and profit

[10% on own work, 5% on subcontract]

[$499]

Bond and insurance

[0.9% of subtotal]

[$57]

Total of this change order

[$6,842]

Attach the subcontractor quotes and any supporting time-and-material sheets.

5. Contract sum

Amount

Original contract sum

[$4,860,000]

Net change by previously authorised change orders (CO 001–006)

[$84,315]

Contract sum before this change order

[$4,944,315]

This change order: ☐ increase ☐ decrease ☐ no change

[$6,842]

New contract sum including this change order

[$4,951,157]

6. Contract time

Change in contract time

☐ Increase ☐ Decrease ☐ No change: [2] working days

Substantial completion date before this change order

[26 Mar 2027]

New substantial completion date

[30 Mar 2027]

7. Terms

  1. This change order, when signed by the Owner and Contractor, amends the contract for the work described. All other terms of the contract remain in full force.

  2. The adjustments in contract sum and contract time above are full and final compensation for all direct and indirect costs and time associated with this change, including any impact on other work, except: [none / state any reserved items].

  3. Work on this change will begin after all signatures are received, unless the Owner gives written authorisation to proceed earlier.

  4. Payment for this change will be included in the next application for payment after the work is complete [or billed by percentage complete].

8. Approvals

Party

Name and title

Signature

Date

Contractor

[Name, Project Manager]

[Date]

Architect / engineer

[Name, Project Architect]

[Date]

Owner

[Name, Owner’s Representative]

[Date]


Optional clauses

  • Not-to-exceed: The Owner authorises the Contractor to proceed on a time-and-material basis not to exceed [$ amount]; a final change order will follow within [10] days of completion.

  • Reservation of rights: The Contractor reserves the right to claim additional time for the cumulative impact of changes, to be submitted by [date].

  • Credit change: For deleted work, the credit equals the Contractor’s cost of the deleted work, with [no / X%] overhead and profit returned.

This template is for general information and is not legal advice. Laws vary by [state/country]; have a qualified lawyer review it before signing.

Text in [brackets] is yours to replace.

  • About
  • What’s included
  • How to use
  • Questions
  • Related resources

About this template

Unsigned changes are the biggest source of construction payment disputes. This change order form records exactly what changed and why, the documents it relates to, a transparent cost breakdown (labour, materials, equipment, subcontract, overhead and profit, bond and insurance), the effect on the contract sum and completion date, and signatures from contractor, architect and owner, so the work is agreed and priced before it is built.

Who it’s for

  • Owner-requested changes and upgrades
  • Unforeseen site conditions
  • Design errors and code-required changes
  • Residential remodels and commercial projects

What’s included

  • 1. Description of change
  • 2. Reason for change
  • 3. References
  • 4. Cost breakdown
  • 5. Contract sum
  • 6. Contract time
  • 7. Terms
  • 8. Approvals
  • Optional clauses

How to use it

  1. 1Number the change order and fill in the project, contract and parties.
  2. 2Describe the change precisely and reference the RFI, ASI, bulletin or drawings it comes from.
  3. 3Price it in the cost breakdown, applying the markups the contract allows.
  4. 4Show the effect on the contract sum and the number of days added or removed.
  5. 5Get every signature before the changed work starts, unless the contract allows a construction change directive.

Tips

  • Agree time as well as money. A change order silent on time can waive a later delay claim.
  • Use the markup percentages in your contract; if none are stated, agree them before pricing the first change.
  • For urgent work, get at least a signed not-to-exceed authorisation and finalise the change order within days.

Questions

What is a change order in construction?

A written amendment to the construction contract, signed by the owner and contractor (and usually the architect), that changes the scope of work, the contract sum, the contract time or a combination.

What is the difference between a change order and a change directive?

A change order is agreed by both parties. A construction change directive (AIA G714) lets the owner order the work before price or time is agreed, with the adjustment settled later.

What markup is normal on change orders?

Commonly 10–15% overhead and profit on self-performed work and 5–10% on subcontracted work, but the contract governs.

Related searcheschange order formconstruction change order templatechange order requestcontract change orderchange order pdfconstruction change order form word

Details

Format
Document
Category
Construction Project Management
Setup
20 min
Level
Intermediate
Price
Free

Download a copy

Downloads need a free account.

DocumentConstruction Project ManagementFree

Change Order Form

Document a change to the construction contract with description, reason, cost breakdown with markup, contract sum reconciliation, time impact and approvals.

A free account keeps your copy safe so you can come back to it. Have one? Log in

Download a copy

Downloads need a free account.

Details

Format
Document
Category
Construction Project Management
Setup
20 min
Level
Intermediate
Price
Free

Your copy is private to you.

More construction project management templates

View all
Construction Project Schedule
Task
SepOctNovDecJanFebMar
Permits and mobilisation
Excavation and footings
Slab pour and cure
Framing and sheathing
Roofing
Windows and exterior doors
SpreadsheetConstruction Project Management

Construction Project Schedule

The build programme with planned and actual dates, progress weighted by duration, behind-schedule flags, a month-by-month bar chart and phase summaries.

10 min setupPreview
RFI Log2 sheets

Open RFIs

4

Overdue responses

2

Average days to answer

10.3

ABCD
1RFIRaisedSubjectCategory
2RFI-001Oct 5Slab edge detail at grid line C clashes with drainageStructural
3RFI-002Oct 9Door D14 hardware schedule missingArchitectural
4RFI-003Oct 20Ceiling void too shallow for specified ductwork, level 2Mechanical & electrical
5RFI-004Oct 28Confirm brick type for east elevation; sample rejectedArchitectural
RFIs
SpreadsheetConstruction Project Management

RFI Log

Track every request for information from question to answer, with due dates and cost and schedule impact.

10 min setupPreview
Schedule of Values & Payment Application2 sheets

Contract sum

$1,200,000

Completed to date

52%

Payment due this application

$173,070

ABCD
1ItemDescription of workCategoryScheduled value
21General conditions and supervisionGeneral conditions$85,000
32Site clearance and excavationSite work$62,000
43Foundations and slabStructure$148,000
54Structural steel frameStructure$215,000
Schedule of values
SpreadsheetConstruction Project Management

Schedule of Values & Payment Application

Bill progress against each line of the contract: work completed, stored materials, retainage and payment due.

10 min setupPreview

Practical guides and new resources, monthly.

One short email with new templates, calculators and how-tos. Unsubscribe any time.

GraviPointThe Centre of Productivity

Find the right resource. Make it work for you. Get things done with spreadsheets, documents, forms and calculators you can use right in your browser.

support@gravipoint.com
  • @gravipoint
  • @GraviPoint
  • GraviPoint
  • 𝕏@gravipoint

Templates

  • All templates
  • Budgets & expenses
  • Invoices & billing
  • Project management
  • HR & people
  • Inventory & stock
  • Sales & CRM
  • Financial calculators

Popular

  • Monthly budget
  • Invoice
  • Employee shift schedule
  • Weekly timesheet
  • Project plan & Gantt chart
  • Inventory tracker
  • Expense report
  • Mortgage calculator

Solutions

  • Individuals & households
  • Freelancers & consultants
  • Founders & startups
  • Small business owners
  • Teams & operations
  • Students & educators

Company

  • About
  • Features
  • Pricing
  • Community
  • Journal
  • Contact
© 2026 GraviPoint. All rights reserved.
  • Privacy
  • Terms
  • Help centre
  • FAQ