Change Order No. [007]
Project | [Riverside Medical Office Building] |
Project address | [1200 River Road, City, State ZIP] |
Contract date | [12 Mar 2026] |
Contract for | [General construction] |
Owner | [Riverside Health Properties LLC] |
Contractor | [Keystone Builders Inc.] |
Architect | [Hale Design Studio] |
Date of this change order | [17 Nov 2026] |
1. Description of change
Describe exactly what is added, deleted or changed, with locations and quantities. Relocate sinks and casework in exam rooms 104, 106 and 108 from the north to the east wall as shown on ASI-009, including relocated waste, vent and water lines in the slab, new wall blocking, patching the slab and moving two electrical receptacles per room.
2. Reason for change
☐ Owner request ☐ Unforeseen site condition ☐ Design error or omission ☐ Code or authority requirement ☐ Value engineering ☐ Other: [ ]
[Owner request to improve clinician workflow following mock-up review on 4 Nov 2026.]
3. References
Document | Number | Date |
|---|---|---|
Architect’s supplemental instruction | [ASI-009] | [6 Nov 2026] |
Contractor’s proposal | [PCO 014] | [17 Nov 2026] |
Drawings affected | [A-201, P-101, E-101] | [Rev 3] |
Related RFI | [None] |
4. Cost breakdown
Item | Quantity and basis | Amount |
|---|---|---|
Labour | [38 h × $72/h (carpentry, demolition, patching)] | [$2,736] |
Materials | [Blocking, slab patch, fittings] | [$640] |
Equipment | [Concrete saw and core drill, 1 day] | [$310] |
Subcontract: plumbing | [Relocate waste, vent and water, 3 rooms] | [$2,180] |
Subcontract: electrical | [Relocate 6 receptacles] | [$420] |
Subtotal | [$6,286] | |
Overhead and profit | [10% on own work, 5% on subcontract] | [$499] |
Bond and insurance | [0.9% of subtotal] | [$57] |
Total of this change order | [$6,842] |
Attach the subcontractor quotes and any supporting time-and-material sheets.
5. Contract sum
Amount | |
|---|---|
Original contract sum | [$4,860,000] |
Net change by previously authorised change orders (CO 001–006) | [$84,315] |
Contract sum before this change order | [$4,944,315] |
This change order: ☐ increase ☐ decrease ☐ no change | [$6,842] |
New contract sum including this change order | [$4,951,157] |
6. Contract time
Change in contract time | ☐ Increase ☐ Decrease ☐ No change: [2] working days |
Substantial completion date before this change order | [26 Mar 2027] |
New substantial completion date | [30 Mar 2027] |
7. Terms
This change order, when signed by the Owner and Contractor, amends the contract for the work described. All other terms of the contract remain in full force.
The adjustments in contract sum and contract time above are full and final compensation for all direct and indirect costs and time associated with this change, including any impact on other work, except: [none / state any reserved items].
Work on this change will begin after all signatures are received, unless the Owner gives written authorisation to proceed earlier.
Payment for this change will be included in the next application for payment after the work is complete [or billed by percentage complete].
8. Approvals
Party | Name and title | Signature | Date |
|---|---|---|---|
Contractor | [Name, Project Manager] | [Date] | |
Architect / engineer | [Name, Project Architect] | [Date] | |
Owner | [Name, Owner’s Representative] | [Date] |
Optional clauses
Not-to-exceed: The Owner authorises the Contractor to proceed on a time-and-material basis not to exceed [$ amount]; a final change order will follow within [10] days of completion.
Reservation of rights: The Contractor reserves the right to claim additional time for the cumulative impact of changes, to be submitted by [date].
Credit change: For deleted work, the credit equals the Contractor’s cost of the deleted work, with [no / X%] overhead and profit returned.
This template is for general information and is not legal advice. Laws vary by [state/country]; have a qualified lawyer review it before signing.