Work Instruction: [Fit and Torque Pump Housing Cover]
WI number | [WI-PA-0412] |
Revision | [C], effective [12 Nov 2026] |
Product / part | [PH-220 pump housing assembly, part 220-1150] |
Operation | [Op 40: Cover fit and torque] |
Workstation | [Line 3, Station 4] |
Cycle time / takt time | [92 seconds / 105 seconds] |
Prepared by | [Process engineer name] |
Approved by | [Production manager] and [Quality engineer] |
1. Purpose
This instruction defines the one best way to fit the cover gasket, seat the cover and torque the six M8 cover bolts on the [PH-220] housing, so that every unit passes the leak test first time and every bolt holds its specified clamp load.
2. Scope
Applies to all operators, trainers and team leaders at [Line 3, Station 4] on all shifts. It does not cover rework of units that fail the leak test (see [WI-PA-0418]).
3. Safety and PPE
Hazard | Control | PPE required |
|---|---|---|
Pinch point between cover and housing | Hold the cover by its edges; keep fingers clear of the joint face | Cut-resistant gloves (ANSI A2 or EN 388 level B) |
Nutrunner reaction torque | Use the torque reaction arm for every bolt | Safety glasses |
Repetitive motion | Rotate stations every 2 hours as shown on the rotation board | None |
Dropped housings (4.2 kg) | Move housings with the lift assist only | Safety shoes |
4. Tools, materials and equipment
Item | Specification | Check before use |
|---|---|---|
Nutrunner | [DC electric tool], program P07, 24 N·m ± 2 | Daily check on the joint simulator, logged on the check sheet |
Verification torque wrench | Click type 5–50 N·m, ID [TW-031] | Calibration label in date |
Gasket | [220-1162], nitrile, single use | No cuts, kinks or contamination |
Cover bolts | M8 × 25, class 8.8, pre-applied threadlocker, [220-1170] | Patch visible; bin label matches the part number |
Cover | [220-1155] | Joint face free of burrs and paint |
5. Step-by-step instructions
# | Major step (what) | Key points (how) | Reasons (why) |
|---|---|---|---|
1 | Scan the housing traveller | Scan the barcode; confirm the screen shows Op 40 and the correct model | Traceability, and the controller loads the right program |
2 | Inspect and clean the joint face | Wipe with a lint-free cloth and IPA; reject nicks longer than 1 mm | Dirt and damage are the main causes of leak failures |
3 | Fit the gasket | Locate on both dowels, part number facing up; never stretch it | A stretched gasket thins out and leaks |
4 | Seat the cover | Lower it straight down onto the dowels; do not slide it across the gasket | Sliding rolls the gasket out of its groove |
5 | Start the bolts by hand | Run all six bolts in 2–3 turns by hand | Prevents cross-threading and stripped threads |
6 | Torque in sequence | Star pattern 1-4-2-5-3-6 as shown on the visual aid; wait for the green light on each bolt | Even clamp load; uneven torque warps the cover |
7 | Confirm the result | Controller must show 6/6 OK; any NOK, go to Section 7 | Under-torqued bolts loosen in service |
8 | Mark and release | Paint-pen line across each bolt head; place the unit on the outfeed conveyor | Visible proof that every bolt was torqued |
Keep each key point to one short line. Add a photo for any step a new operator gets wrong.
6. Quality checks
Characteristic | Specification | Method | Frequency | Record |
|---|---|---|---|---|
Bolt torque | 24 N·m ± 2 | Nutrunner controller | Every bolt | Controller data (automatic) |
Torque audit | 22–26 N·m breakaway | Calibrated click wrench | 1 unit per hour | Hourly check sheet |
Gasket position | Fully in groove, nothing visible outside the cover | Visual | Every unit | None unless rejected |
Paint marks | 6 marks present | Visual | Every unit | None unless rejected |
7. Reaction plan: if something is wrong
Stop. Do not pass the unit to the next station.
Put the unit on the red rack and attach a red HOLD tag stating the fault.
Call the team leader on the andon: yellow for quality, red for safety.
Do not re-torque a bolt that reported NOK. The team leader decides whether to replace the bolt and gasket.
If two NOKs occur within one hour, the team leader stops the station and calls maintenance and quality.
8. Visual aids and references
Torque sequence diagram: [VA-PA-0412-1]
Gasket orientation photo: [VA-PA-0412-2]
Control plan: [CP-PH220, Op 40]
Process FMEA: [PFMEA-PH220, lines 40.1–40.6]
9. Training record
Operator | Trained by | Date | Level (1 learning, 2 supervised, 3 independent, 4 can train) |
|---|---|---|---|
[Name] | [Trainer] | [Date] | [3] |
[Name] | [Trainer] | [Date] | [2] |
10. Revision history
Rev | Date | Change | Approved by |
|---|---|---|---|
A | [Mar 2026] | First issue | [Name] |
B | [Jul 2026] | Added hourly torque audit after customer complaint [26-118] | [Name] |
C | [Nov 2026] | New nutrunner program P07; star sequence clarified | [Name] |