Feasibility Study: [Central Production Kitchen]
Organisation | [Saffron & Sage Restaurant Group (6 restaurants)] |
Sponsor | [Name, Chief Operating Officer] |
Prepared by | [Name, Operations Projects Manager] |
Date | [December 2026] |
Decision required by | [Board meeting, 28 January 2027] |
1. Executive summary
[The group asked whether a central production kitchen (CPK) preparing sauces, stocks, desserts and pre-portioned proteins for all six restaurants is feasible. We assessed three options against a do-nothing baseline. A leased 4,000 sq ft CPK (Option B) is feasible with conditions: it requires $640,000 of investment, saves an estimated $395,000 a year from year 2, and pays back in about 2.1 years. The main conditions are securing a site with suitable drainage and extraction, and retaining two head chefs to lead production. We recommend proceeding to a full business case and site search.]
2. Background and objectives
[Food cost has risen from 29% to 33% of sales in two years. Each restaurant prepares its own base recipes, causing inconsistent quality, waste and duplicated skilled labour in a tight market for chefs.]
Objectives of the study:
[Determine whether a CPK can reduce food and labour cost by at least 2.5 points of sales.]
[Confirm quality and food-safety standards can be maintained or improved.]
[Identify the preferred option, cost, risks and timeline.]
Out of scope: [Menu redesign, new restaurant openings, retail products.]
3. Options considered
Option | Description |
|---|---|
A. Do nothing | [Each restaurant continues to prepare everything on site] |
B. Leased CPK | [Lease and fit out a 4,000 sq ft unit within 25 minutes of all sites] |
C. Use one restaurant kitchen as hub | [Extend the largest restaurant’s kitchen to supply the others] |
D. Outsource to a contract caterer | [Buy sauces, stocks and desserts from a third-party manufacturer] |
4. Market and demand feasibility
[Volumes: the six restaurants serve 14,200 covers a week; 62% of dishes use at least one base component suitable for central production.]
[Customer impact: guest survey (n = 640) shows consistency is the top complaint after price; 71% would not notice central preparation if quality is maintained.]
[Growth: two further restaurants are planned by 2029, which a CPK could supply without extra prep kitchens.]
Rating: [Feasible]
5. Technical and operational feasibility
Factor | Finding | Rating |
|---|---|---|
[Site availability] | [3 suitable industrial units identified; 1 has grease-trap drainage already] | [Feasible with conditions] |
[Equipment] | [Blast chillers, combi ovens, tilting kettle, vacuum packer: proven, 8–12 week lead times] | [Feasible] |
[Logistics] | [One refrigerated van, two daily runs; route modelled at 2 h 40 min] | [Feasible] |
[Shelf life] | [Most components 3–5 days chilled; desserts 7 days; validated by external lab for 4 recipes] | [Feasible with conditions] |
[Option C capacity] | [Hub kitchen would need 60% more space; building owner refused extension] | [Not feasible] |
6. Financial feasibility
Item | Option B: Leased CPK | Option D: Outsource |
|---|---|---|
One-off investment | [$640,000 (fit-out $410k, equipment $190k, van $40k)] | [$25,000 (transition, trials)] |
Annual running cost | [$585,000 (rent, staff, utilities, logistics)] | [$0 extra; higher purchase prices] |
Annual savings (from year 2) | [$395,000 net (labour $260k, waste $85k, purchasing $95k, less $45k transport)] | [$110,000 net] |
Payback | [About 2.1 years] | [Under 1 year] |
5-year net benefit (undiscounted) | [$1.21m] | [$0.42m] |
Full cash flows and assumptions are in Appendix A. Savings are most sensitive to labour: if only half the planned prep hours are removed, payback extends to 3.4 years.
Rating: [Option B feasible; Option D feasible but delivers a third of the benefit and less control over quality]
7. Legal and regulatory feasibility
[Food business registration and approval for the new premises with the local authority: typically 28 days after application. [Requirements vary by jurisdiction.]]
[HACCP plan required for cook-chill processes, with validated chilling times and labelling (allergens, use-by dates).]
[Planning use class allows food production at 2 of the 3 shortlisted sites.]
[Lease: 10 years with a break at year 5; landlord consent needed for extraction.]
Rating: [Feasible with conditions]
8. Organisational feasibility
[Requires a Production Manager and 9 production staff; 6 roles can be filled by redeploying prep chefs from restaurants.]
[Head chefs are supportive if they keep control of finishing and specials; two senior chefs have volunteered to lead production.]
[Union or staff consultation: [required/not required] for changes to working location.]
Rating: [Feasible with conditions]
9. Schedule feasibility
Milestone | Target date |
|---|---|
[Board approval of business case] | [March 2027] |
[Lease signed] | [May 2027] |
[Fit-out complete] | [September 2027] |
[Food business approval and trials] | [October 2027] |
[Phased supply to all six restaurants] | [November 2027 – January 2028] |
Rating: [Feasible: avoids changing kitchens during the December peak by phasing the last two sites into January.]
10. Key risks
Risk | Likelihood | Impact | Mitigation |
|---|---|---|---|
[Fit-out overruns cost or time] | [Medium] | [High] | [Fixed-price contract; 12% contingency] |
[Quality drops and chefs resist] | [Medium] | [High] | [Chef-led recipe trials; finishing stays in restaurants] |
[Single point of failure: CPK outage stops supply] | [Low] | [High] | [Two days’ buffer stock; restaurant fallback recipes] |
[Savings overstated] | [Medium] | [Medium] | [Phase benefits; track labour hours per cover monthly] |
11. Feasibility summary
Dimension | Option A | Option B | Option C | Option D |
|---|---|---|---|---|
Market | [n/a] | [Feasible] | [Feasible] | [Feasible] |
Technical and operational | [Feasible] | [With conditions] | [Not feasible] | [Feasible] |
Financial | [Costs keep rising] | [Feasible] | [n/a] | [Feasible, low benefit] |
Legal and regulatory | [Feasible] | [With conditions] | [n/a] | [Feasible] |
Organisational | [Feasible] | [With conditions] | [n/a] | [Chef concerns on quality] |
Schedule | [n/a] | [Feasible] | [n/a] | [Feasible] |
12. Recommendation
[Proceed with Option B: Leased CPK to full business case, subject to these conditions:]
[A site with approved food-production use and suitable drainage is secured within budget.]
[Shelf-life validation is completed for all 22 planned components.]
[Two senior chefs commit to production leadership roles.]
13. Next steps
Action | Owner | Due |
|---|---|---|
[Prepare full business case with detailed cash flows] | [Finance Director] | [28 Feb 2027] |
[Shortlist and survey sites; obtain fit-out quotes] | [Operations Projects Manager] | [28 Feb 2027] |
[Complete shelf-life testing] | [Executive Chef] | [31 Mar 2027] |
[Staff consultation plan] | [Head of People] | [31 Mar 2027] |
Appendices
[A. Financial model and assumptions]
[B. Site survey summaries]
[C. Guest survey results]
[D. Regulatory checklist]